Demand is Key: Rescission Rights in Philippine Contract Law

,

The Supreme Court in Solar Harvest, Inc. v. Davao Corrugated Carton Corporation, G.R. No. 176868, July 26, 2010, held that a prior demand for fulfillment is generally required before a party can claim rescission of a reciprocal obligation under Article 1191 of the Civil Code. This means that before a buyer can demand their money back due to non-delivery, they must first formally ask the seller to deliver the goods; absent such demand, there is no breach of contract and thus, no basis for rescission. The ruling emphasizes the importance of formal demand in establishing default in contractual obligations.

Carton Conundrum: Who Bears the Burden of Delivery?

In 1998, Solar Harvest, Inc. (petitioner) and Davao Corrugated Carton Corporation (respondent) agreed on the purchase of custom-made corrugated carton boxes for Solar Harvest’s banana export business, priced at US$1.10 each. Solar Harvest made a full payment of US$40,150.00 for the boxes. However, no boxes were ever received by Solar Harvest.

Three years later, Solar Harvest demanded reimbursement of their payment. Davao Corrugated responded that the boxes were completed in April 1998 and that Solar Harvest failed to pick them up as agreed. The company also claimed Solar Harvest had placed an additional order, part of which was completed. Solar Harvest then filed a complaint seeking the sum of money and damages, claiming the agreement stipulated delivery within 30 days of payment. Davao Corrugated countered that the agreement required Solar Harvest to pick up the boxes and that they were owed money for the additional order and storage fees.

The central legal question revolves around whether Davao Corrugated was obligated to deliver the boxes, and whether Solar Harvest had properly demanded fulfillment of that obligation before seeking rescission of the contract. The resolution of this issue hinges on the interpretation of the agreement between the parties and the application of Articles 1191 and 1169 of the Civil Code concerning reciprocal obligations and delay.

Article 1191 of the Civil Code provides the basis for rescission of reciprocal obligations:

Art. 1191. The power to rescind obligations is implied in reciprocal ones, in case one of the obligors should not comply with what is incumbent upon him.

The injured party may choose between the fulfillment and the rescission of the obligation, with the payment of damages in either case. He may also seek rescission, even after he has chosen fulfillment, if the latter should become impossible.

The court shall decree the rescission claimed, unless there be just cause authorizing the fixing of a period.

This is understood to be without prejudice to the rights of third persons who have acquired the thing, in accordance with Articles 1385 and 1388 and the Mortgage Law.

However, the right to rescind is not absolute. It is governed by Article 1169, which defines delay:

Art. 1169. Those obliged to deliver or to do something incur in delay from the time the obligee judicially or extrajudicially demands from them the fulfillment of their obligation.

However, the demand by the creditor shall not be necessary in order that delay may exist:

(1) When the obligation or the law expressly so declares; or

(2) When from the nature and the circumstances of the obligation it appears that the designation of the time when the thing is to be delivered or the service is to be rendered was a controlling motive for the establishment of the contract; or

(3) When demand would be useless, as when the obligor has rendered it beyond his power to perform.

In reciprocal obligations, neither party incurs in delay if the other does not comply or is not ready to comply in a proper manner with what is incumbent upon him. From the moment one of the parties fulfills his obligation, delay by the other begins.

The Supreme Court emphasized that in reciprocal obligations, such as a contract of sale, the general rule is that fulfillment should be simultaneous. However, if different dates are fixed for performance, demand is necessary to establish delay. The Court found that Solar Harvest failed to present evidence of a prior demand for delivery before filing the complaint. The alleged “follow-up” did not constitute a formal demand as required by law.

Furthermore, the Court found that Davao Corrugated had indeed manufactured the boxes. The testimony of witnesses and the willingness of Davao Corrugated to allow an ocular inspection of the boxes supported this finding. Additionally, the Court determined that the agreement required Solar Harvest to pick up the boxes from Davao Corrugated’s warehouse. Solar Harvest’s claim that Davao Corrugated was obligated to deliver the boxes was not substantiated by the evidence.

The Supreme Court highlighted the principle that the existence of a breach of contract is a factual matter, and the Court typically defers to the factual findings of the lower courts, especially when affirmed by the Court of Appeals. The Court found no compelling reason to deviate from this principle in this case.

The Court stated:

Even assuming that a demand had been previously made before filing the present case, petitioner’s claim for reimbursement would still fail, as the circumstances would show that respondent was not guilty of breach of contract.

The implications of this ruling are significant for businesses engaged in contracts involving the sale of goods. It underscores the importance of clearly defining the terms of the agreement, particularly regarding delivery. It also highlights the necessity of making a formal demand for fulfillment before seeking rescission of the contract. Failure to do so may result in the denial of the rescission claim.

FAQs

What was the key issue in this case? The key issue was whether Solar Harvest had a valid cause of action for rescission of contract against Davao Corrugated due to alleged non-delivery of goods. The court focused on whether a prior demand for delivery was made.
What is rescission of contract? Rescission is a legal remedy that cancels a contract and restores the parties to their original positions, as if the contract never existed. It is available when one party fails to fulfill their obligations in a reciprocal agreement.
What is a reciprocal obligation? A reciprocal obligation is one where the obligations of one party are correlated with the obligations of the other party. In a sale, the seller delivers the goods, and the buyer pays for them.
Why was demand important in this case? Demand is crucial because, under Article 1169 of the Civil Code, a party incurs delay only from the time the other party demands fulfillment of the obligation. Without demand, there is no breach, and rescission is not justified.
What evidence did Solar Harvest lack? Solar Harvest lacked evidence of a formal demand for delivery made upon Davao Corrugated before filing the complaint for rescission. The court found that the follow-ups made were insufficient to constitute a formal demand.
What did the court decide regarding the delivery of the boxes? The court determined that the agreement required Solar Harvest to pick up the boxes from Davao Corrugated’s warehouse, rather than Davao Corrugated being obligated to deliver them. This was a key factor in denying Solar Harvest’s claim.
What happens to the boxes now? The court ordered Solar Harvest to remove the boxes from Davao Corrugated’s warehouse within 30 days; if they fail to do so, Davao Corrugated has the right to dispose of them.
What is the practical implication of this case? The case emphasizes the importance of clearly defining delivery terms in contracts and making a formal demand before seeking rescission. It serves as a reminder that clear communication and documentation are essential in contractual relationships.

This case underscores the importance of clear contractual terms and the necessity of proper demand before seeking legal remedies such as rescission. Businesses should ensure their agreements clearly define obligations and establish procedures for communication and demand to avoid similar disputes.

For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.

Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: Solar Harvest, Inc. v. Davao Corrugated Carton Corporation, G.R. No. 176868, July 26, 2010

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *