The Supreme Court affirmed that a construction contract is perfected when the contract is awarded to the bidder, irrespective of a subsequent temporary suspension, binding the parties to fulfill their obligations. This ruling clarifies that a mere temporary suspension does not nullify an existing agreement, and parties are entitled to damages if one party fails to comply with their contractual duties. It reinforces the principle that an award signifies acceptance, creating a binding contract that must be honored, safeguarding the interests of contractors and project owners alike.
From First Notice to Final Claims: Decoding a Contract’s Fate
This case, Metro Rail Transit Development Corporation v. Gammon Philippines, Inc., revolves around the MRT-3 North Triangle Development Project, where Gammon Philippines, Inc. (Gammon) was awarded the contract for the Podium structure. However, due to financial fluctuations, the project faced temporary suspension. This led to disputes over whether a perfected contract existed and whether Gammon was entitled to damages for lost profits and reimbursements. The central legal question is whether the initial award of the contract constituted a perfected agreement, binding both parties despite the subsequent suspension and eventual cancellation of the project.
The narrative begins with Gammon receiving an invitation to bid for the complete concrete works of the Podium, part of the MRT-3 project. Parsons Interpro JV (Parsons), the Management Team, oversaw the construction. Gammon won the bid, and on August 27, 1997, Parsons issued a Letter of Award and Notice to Proceed (First Notice to Proceed) to Gammon. The First Notice outlined the scope of work, amounting to P1,401,672,095.00. It stipulated that work would be divided into two phases due to existing squatters, but treated as one contract. Gammon was instructed to proceed with Phase I, subject to site de-watering and clean-up.
In response, on September 2, 1997, Gammon signed and returned the First Notice to Proceed, confirming their mobilization efforts and design activities. A signed Letter of Comfort, guaranteeing Gammon’s obligations, followed on September 3, 1997. However, on September 8, 1997, MRT informed Gammon of a temporary delay due to foreign exchange rate issues. Parsons then directed Gammon to halt mobilization activities. Despite this, Gammon asserted the existence of a valid contract, citing their acceptance of the First Notice and their commitment to commence work.
As the situation evolved, MRT decided to downscale the Podium’s construction, leading to conceptual redesigns. Gammon, upon Parson’s request, proposed phasing options. MRT eventually opted for constructing the Podium up to Level 2 only, necessitating redesign of the Level 2 slab. On February 18, 1998, Parsons issued a Second Notice to Proceed for engineering services based on the redesigned plan, with a provision for reimbursement of incurred expenses. Gammon signed this notice, emphasizing the validity of the initial Notice of Award.
Later developments included a Revised Lump Sum Price Proposal from Gammon and further communications regarding extra contract expenses. On April 2, 1998, MRT issued a Third Notice to Proceed, followed by Gammon’s request for clarifications. However, on May 7, 1998, Parsons informed Gammon that MRT was temporarily rescinding the Third Notice. Eventually, on June 11, 1998, Gammon received a Fourth Notice to Proceed with differing terms, which expressly cancelled the previous notices. Gammon qualifiedly accepted the Fourth Notice, which MRT rejected, threatening to award the contract to Filsystems if Gammon did not accept unconditionally.
The situation culminated in Gammon notifying MRT of claims for costs, losses, and damages incurred due to the project’s mobilization and subsequent cancellation. MRT expressed disagreement but offered reimbursement for bid participation costs, which Gammon deemed insufficient. After unsuccessful negotiations, Gammon filed a Notice of Claim before the Construction Industry Arbitration Commission (CIAC). This led to legal battles, including a Supreme Court decision affirming CIAC’s jurisdiction. The CIAC ruled in favor of Gammon, awarding monetary claims for lost profits and reimbursements, a decision affirmed by the Court of Appeals.
The central issue before the Supreme Court was whether a perfected contract existed between MRT and Gammon. The Court emphasized that a contract is perfected when there is a meeting of minds between two parties, and one binds himself with respect to the other to give something or render some service. Consent is shown when one party’s offer is absolutely accepted by the other. The court found that MRT’s First Notice to Proceed constituted an acceptance of Gammon’s bid, creating a perfected contract. MRT argued that the contract was revoked before Gammon’s acceptance. However, the Court clarified that the temporary suspension did not amount to a revocation. The Court referenced Article 1305 of the Civil Code, which defines a contract as a meeting of minds whereby one binds himself to the other, and Article 1315, stating that contracts are perfected by mere consent.
Article 1305. A contract is a meeting of minds between two persons whereby one binds himself, with respect to the other, to give something or to render some service.
Article 1315. Contracts are perfected by mere consent, and from that moment the parties are bound not only to the fulfillment of what has been expressly stipulated but also to all the consequences which, according to their nature, may be in keeping with good faith, usage and law.
Gammon’s prompt response to the First Notice, including the signed notice and subsequent actions to mobilize resources, demonstrated their acceptance of the contract’s terms. MRT’s argument of revocation was weakened by their own communications indicating a temporary suspension rather than a complete cancellation. Furthermore, MRT’s express cancellation of the contract in the Fourth Notice to Proceed implied that the prior notices were still valid up until that point. These circumstances led the court to conclude that a perfected contract existed, obligating both parties to its terms. The Court stated that under Article 1318 of the Civil Code, the requisites of a valid contract include: (1) consent of the contracting parties; (2) object certain which is the subject matter of the contract; and (3) cause of the obligation which is established.
(1) Consent of the contracting parties;
(2) Object certain which is the subject matter of the contract;
(3) Cause of the obligation which is established.
The court addressed the application of the doctrine of the law of the case, stemming from a prior decision, Gammon v. Metro Rail Transit Development Corporation. While that case primarily concerned CIAC’s jurisdiction, the Supreme Court clarified that CIAC’s jurisdiction extends to disputes arising from construction contracts, even if the contract is terminated. The court ruled that the prior determination that there was no novation of the original agreement indicated that a contractual obligation existed. According to the doctrine of the law of the case, a principle of law determined by an appellate court becomes binding in all subsequent stages of the same case.
The court also upheld CIAC’s award of reimbursement for engineering services, design work, site de-watering, and clean-up. MRT had expressed its willingness to pay Gammon for these costs in its Answer with Compulsory Counterclaim. The Court deemed this a judicial admission, binding on MRT. Rule 129, Section 4 of the Revised Rules of Court states that “An admission, verbal or written, made by a party in the course of the proceedings in the same case, does not require proof.” As MRT failed to show that its admission was made through palpable mistake, it was estopped from denying its representation.
Section 4. Judicial admissions. An admission, verbal or written, made by a party in the course of the proceedings in the same case, does not require proof. The admission may be contradicted only by showing that it was made through palpable mistake or that no such admission was made.
Regarding the award of lost profits, the court affirmed that actual damages must be proven with a reasonable degree of certainty. Though official receipts are the best evidence, the Court noted that damages may be proved by other documentary evidence, including invoices. Although challenging the reliability of Gammon’s witness and the documentary evidence, the Court deferred to CIAC’s expertise in construction disputes, recognizing that arbitration proceedings are not strictly bound by technical rules of evidence. The arbitration body is to determine the facts of each case by all reasonable means without regard to technicalities of law or procedure. Under Section 13.5 of the CIAC Revised Rules of Procedure Governing Construction Arbitration, the Arbitral Tribunal is empowered to ascertain the facts in each case by every and all reasonable means without regard to technicalities of law or procedure, thus, the findings of fact of CIAC are binding, respected, and final.
FAQs
What was the key issue in this case? | The key issue was whether a perfected contract existed between Metro Rail Transit Development Corporation (MRT) and Gammon Philippines, Inc. (Gammon) despite a temporary suspension of the project. |
When is a construction contract considered perfected? | A construction contract is perfected when the offer of one party is absolutely accepted by the other, often signified by the award of the contract to the bidder. |
Does a temporary suspension nullify a perfected contract? | No, a temporary suspension of a contract does not nullify it; it merely suspends its operative effect until the suspension is lifted. |
What is the doctrine of the law of the case? | The doctrine of the law of the case provides that a legal issue determined by an appellate court is binding in all subsequent stages of the same case. |
What constitutes a judicial admission? | A judicial admission is a statement made by a party in the course of legal proceedings that is binding and does not require further proof. |
How are actual damages proven in a construction dispute? | Actual damages must be proven with a reasonable degree of certainty, using competent evidence such as official receipts or other documentary evidence like invoices. |
Are arbitration proceedings bound by strict rules of evidence? | No, arbitration proceedings, particularly those under CIAC, are not strictly bound by technical rules of evidence, allowing arbitrators to ascertain facts through all reasonable means. |
What is CIAC’s role in construction disputes? | CIAC has original and exclusive jurisdiction over disputes arising from construction contracts, providing a specialized forum for resolving such issues. |
Can findings of fact by CIAC be reviewed on appeal? | Generally, findings of fact by CIAC are final and not reviewable on appeal, except in specific circumstances such as fraud, corruption, or grave abuse of discretion. |
In summary, the Supreme Court’s decision underscores the importance of honoring contractual obligations once a contract is perfected. A temporary suspension does not erase the binding agreement, and parties are entitled to compensation for losses incurred due to breach of contract. This case reinforces the legal framework governing construction contracts, ensuring fairness and accountability in the industry.
For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.
Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: METRO RAIL TRANSIT DEVELOPMENT CORPORATION V. GAMMON PHILIPPINES, INC., G.R. No. 200401, January 17, 2018