In a contract dispute between B.F. Corporation (BFC) and Form-Eze Systems Inc. concerning the lease of construction equipment for the SM City-Marikina mall project, the Supreme Court held that BFC was not obligated to pay the full contract price because Form-Eze failed to supply the minimum quantity of equipment stipulated in their agreement. The Court reinforced the principle of unjust enrichment, preventing Form-Eze from receiving payment for services or equipment not adequately provided, and highlighting the importance of fulfilling contractual obligations to merit compensation. This decision protects contractors from paying for unfulfilled services, affirming fairness in construction agreements.
When Formwork Falls Short: Gauging Fair Payment in Construction Leases
B.F. Corporation (BFC) entered into several contracts with Form-Eze Systems Inc. for the lease of formwork and related equipment for the SM City-Marikina mall project. A dispute arose regarding the amount BFC owed Form-Eze, with BFC arguing that Form-Eze did not supply the full quantity of equipment as stipulated in their contracts, particularly Contract No. 1. The central legal question before the Supreme Court was whether BFC should pay the full contract price despite Form-Eze’s alleged failure to meet its contractual obligations.
The Construction Industry Arbitration Commission (CIAC) initially ruled in favor of Form-Eze, ordering BFC to pay the full contract amount. However, BFC contested this decision, arguing that the CIAC’s findings were not supported by the evidence and that Form-Eze had not provided the agreed-upon quantity of equipment. The Court of Appeals affirmed the CIAC’s decision, prompting BFC to elevate the case to the Supreme Court.
The Supreme Court began its analysis by emphasizing that while the CIAC’s decisions are generally final and binding, they are still subject to judicial review under certain circumstances. Specifically, the Court noted that factual findings of construction arbitrators may be reviewed in cases involving fraud, corruption, or grave abuse of discretion. Additionally, the Court asserted that the Court of Appeals is not precluded from reviewing findings of fact, and in this case, it was necessary to examine the CIAC’s factual findings to ensure an equitable and just award.
Examining Contract No. 1, the Court found that Form-Eze was indeed unable to supply BFC with deckforms sufficient to provide 7,000 contact square meters of formworks, as required by the contract. The Court sided with BFC’s argument that the CIAC should not have included unassembled truss chords in its calculation of the total contact area. According to the Court, the contract specified the supply of complete deckform systems, not merely the hardware components. Moreover, the agreement stipulated that equipment rental payments were due when concrete was placed on the slab forms, implying that the hardware should have been assembled into deckforms before payment was required.
“Contract No. 1, in itself, is clear that ‘F-E has agreed to furnish all hardware required in the formwork system for the poured in place beam and slab concrete decks x x x.’ In fact, the equipment rental is only due and payable to Form-Eze when the concrete is placed on the slab forms, which provision is based on the premise that the hardware had already been assembled into deckforms ready for concrete pouring.”
The Court also highlighted that loose truss chords alone could not be assembled into deckforms without additional components such as joists and beam hangers. BFC provided evidence, including delivery receipts, to support its computation of the total contact area covered by the deckforms furnished by Form-Eze. In contrast, the CIAC’s computation was deemed more theoretical than practical. However, the Court agreed with the CIAC’s inclusion of the contact area of grid girders in the calculation, referencing a letter agreement between the parties. This agreement stipulated that Form-Eze would include the contact square meters of formwork in the girders in its billing for both the equipment lease and the moving contract.
Even with the inclusion of the grid girders’ contact area, the total contact area still fell short of the 7,000 contact area requirement stipulated in Contract No. 1. As a result, the Court found that awarding the full contract price to Form-Eze would amount to unjust enrichment. The principle of **unjust enrichment**, as outlined in Article 22 of the Civil Code, states that a person should not be unjustly benefited at the expense of another. In this case, requiring BFC to pay the full contract price when Form-Eze had not fully met its contractual obligations would unjustly enrich Form-Eze. The Court emphasized that Form-Eze had only been claiming payment for the contact area where its equipment was actually used.
Turning to the issue of contract reformation, the Court noted that an action for reformation of a contract is grounded on Article 1359 of the New Civil Code. This article allows for the reformation of a written instrument when the true intention of the parties is not expressed due to mistake, fraud, inequitable conduct, or accident. The Court found that the parties had indeed intended to include a labor-guarantee provision in Contract No. 1, as evidenced by their contemporaneous and subsequent acts, as well as the inclusion of such provisions in Contracts No. 2 and 3. The failure to include this provision in Contract No. 1 was deemed a mistake, warranting reformation of the contract.
The Court further addressed the expenses for x-bracing and the cost of labor under Contracts No. 2 and 3. Except for the expenses for x-bracing used in deck assemblies, which were admitted by Form-Eze’s President, James Franklin, the Court held that BFC was not entitled to reimbursement for the cost of helmets, petroleum, and oil lubricants due to the absence of stipulations in the contracts. However, the cost of labor should be deducted pursuant to the labor-guarantee provisions in Contracts No. 2 and 3.
Regarding the Memorandum of Agreement dated January 5, 2007, the Court clarified that it constituted an exclusive licensing agreement, wherein BFC agreed to sell the scaffolding frames and accessories it manufactured to Form-Eze at the end of the project. This agreement was incorporated into Contract No. 4, which allowed BFC to deduct a certain amount from the equipment lease contract. The Court stated that this arrangement could not be interpreted as part of the deckform supplied by Form-Eze, as the scaffoldings and accessories were BFC’s responsibility under Contract No. 1.
Consequently, the Court determined that BFC was only liable to pay for the proportionate amount of forklifts used under Contract No. 2, based on the actual contact square meters covered. Similarly, the Court found that the CIAC’s award regarding Contract No. 3 lacked bases, as Form-Eze had failed to comply with the minimum requirements. The Court emphasized that the ambiguity in Contract No. 3 should not favor Form-Eze, the party who prepared the contract. Therefore, BFC was only liable to pay a reduced amount for Contract No. 3.
Under the letter agreement dated January 5, 2007, the Court upheld BFC’s obligation to pay rental for the u-heads, as BFC had failed to return the equipment within the agreed-upon timeframe. The Court found that the monthly rental amount of P96,600.00 was substantiated by Form-Eze and that BFC had acquiesced to the rental fee by agreeing to the terms of the letter agreement.
Finally, the Court addressed the inclusion of BFC’s President, Honorio Pineda, as a party to the case. The Court noted that Pineda signed the contracts in his capacity as President of BFC and that there was no indication that he voluntarily submitted himself as a party to the arbitration case. Therefore, the Court held that Pineda should not be included as a party to the case. The Court also ruled that both parties should equally share the costs of arbitration, as their prayers were only partially granted.
FAQs
What was the key issue in this case? | The key issue was whether B.F. Corporation (BFC) should pay Form-Eze Systems Inc. the full contract price for leased construction equipment when Form-Eze failed to supply the minimum quantity stipulated in their agreements. |
What is the principle of unjust enrichment? | Unjust enrichment, as defined in Article 22 of the Civil Code, occurs when a person is unjustly benefited at the expense of another, implying that someone should not receive payment for services or goods not adequately provided. |
Why did the Supreme Court modify the CIAC’s decision? | The Supreme Court modified the CIAC’s decision because the CIAC’s findings were not fully supported by the evidence, and the initial ruling would have resulted in unjust enrichment for Form-Eze. |
What was Contract No. 1 about and what was the dispute? | Contract No. 1 was for the lease of equipment for beam and slab hardware for formwork. The dispute centered on whether Form-Eze supplied enough deckforms to meet the 7,000 contact square meter requirement. |
Why did the Court order a reformation of Contract No. 1? | The Court ordered the reformation of Contract No. 1 to include a labor-guarantee provision because both parties intended to include it, but it was mistakenly omitted, as evidenced by similar provisions in other contracts. |
Was BFC’s president, Honorio Pineda, held personally liable? | No, the Court ruled that Honorio Pineda should not be included as a party to the case because he signed the contracts in his capacity as the President of BFC and did not voluntarily submit himself to arbitration. |
What was the outcome regarding the costs of arbitration? | The Court ruled that both BFC and Form-Eze should equally share the costs of arbitration since their claims were only partially granted. |
What was the significance of the letter agreement dated January 5, 2007? | The letter agreement constituted an exclusive licensing agreement where BFC would manufacture scaffolding frames and accessories and sell them to Form-Eze, impacting how certain equipment was accounted for under the contracts. |
In conclusion, the Supreme Court’s decision underscores the importance of fulfilling contractual obligations and adhering to the principle of unjust enrichment in construction contracts. The ruling provides clarity on how payments should be calculated when equipment is leased but not fully utilized, and it highlights the circumstances under which a contract can be reformed to reflect the true intentions of the parties.
For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.
Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: B.F. CORPORATION vs. FORM-EZE SYSTEMS, INC., G.R. No. 192948, December 7, 2016