The Supreme Court has affirmed that contractors performing work for government agencies must strictly adhere to the requirements for obtaining approval for extra work orders. This means that contractors who undertake additional work without prior authorization from the appropriate government officials risk not being compensated for those services. This ruling underscores the importance of following proper procedures and ensuring that all extra work is formally approved before commencing, safeguarding public funds and ensuring accountability in government projects.
Beyond the Blueprint: When Unapproved Changes Leave Contractors Unpaid
The case of Domingo F. Estomo vs. Civil Service Commission revolves around a construction project for the Civil Service Commission (CSC) Regional Office No. X. Engr. Domingo F. Estomo, the contractor, sought payment for additional work he claimed to have performed on the project, which was not explicitly covered in the original contract. The central legal question is whether Estomo is entitled to compensation for these extra works despite not having obtained prior approval as required by government regulations. This case highlights the critical importance of adhering to the strict requirements governing government contracts, particularly those involving extra work orders.
The facts of the case reveal that Estomo was awarded a contract for the construction of the third floor of the CSC Region X building. As the project progressed, Estomo identified the need for additional works, such as wall partitions and kitchen cabinets, and notified the CSC through letters. However, he commenced these extra works without securing formal approval from the CSC. Upon completion of the project, Estomo sought payment for these additional works, but the CSC only approved a portion of his claim, leading to a dispute.
The Regional Trial Court (RTC) initially ruled in favor of Estomo, ordering the CSC to pay the outstanding balance, including the cost of the extra works. However, the Court of Appeals (CA) reversed the RTC’s decision, holding that Estomo was not entitled to payment for the unapproved extra works, because Estomo failed to substantiate his claim. According to the CA, CSC’s obligation to Estomo was deemed extinguished. The CA emphasized that the letters from Estomo to CSC regarding extra work were merely requests, not approvals.
The Supreme Court, in its analysis, delved into the relevant laws and regulations governing government infrastructure contracts. The Court highlighted that Presidential Decree (P.D.) No. 1594 and its implementing rules and regulations (IRR) govern such contracts, emphasizing the need for prior approval for any extra work or change orders. The pertinent provision of P.D. No. 1594 states:
Under no circumstances shall a contractor proceed to commence work under any change order, extra work order or supplemental agreement unless it has been approved by the Secretary or his duly authorized representative.
Building on this principle, the Court noted that Estomo’s letters to the CSC were merely requests or suggestions, and there was no evidence of formal approval for the extra works before they were undertaken. The CSC only approved the amount of P144,735.98 for the extra works, not Estomo’s claimed P261,963.82. According to the Court, payments for extra works cannot be collected on the basis of letter requests and billings alone. The 1992 IRR of P.D. No. 1594 requires that request for payment by the contractor for any extra work shall be accompanied by a statement, with approved supporting forms, giving a detailed accounting and record of amount for which he claims payment.
Estomo invoked the principle of quantum meruit, arguing that the government would be unjustly enriched if he was not compensated for the extra works that benefited the CSC. The Court rejected this argument, distinguishing it from previous cases where quantum meruit was applied. In those cases, the knowledge and consent of the contracting office or agency were clearly established, and the actual work and delivery of results were acknowledged. In Estomo’s case, the CSC did not approve the extra works, and there was no implied contract for these additional services.
Furthermore, the Supreme Court addressed the deductions made by the CSC from Estomo’s payments. The Court found that the deductions for retention money and recoupment of advance payments were valid, as they were in accordance with the applicable rules and regulations. However, the Court clarified that the withholding taxes should have been computed on the gross amount of each progress payment before deducting the retention money. Since the progress payments have already been released to Estomo, the more practical remedy to resolve the issue of the underpayment is to withhold the corresponding 6% VAT on the retention money due to Estomo.
The Court also addressed the release of retention money. While Estomo was entitled to the release of the retention money, the Court noted that the CSC had also deducted an amount for deficiencies in the project. The Court reasoned that these deficiencies served the same purpose as the retention money, ensuring that the project was completed according to specifications. Because the CSC had already been in possession of the project since 1997, the interest of the government is sufficiently protected with the deduction of deficiencies computed at P82,000.00. To further withhold the retention money would sanction unjust enrichment in favor of the government, to the prejudice of Estomo.
In conclusion, the Supreme Court partially granted Estomo’s petition. The Court affirmed the CA’s decision that Estomo was not entitled to payment for the unapproved extra works but modified the ruling to address the improper computation of withholding taxes and the release of retention money. The Court ordered the CSC to release the retention money to Estomo, subject to the deduction of the underpaid VAT, and remanded the case to the RTC for proper computation of the total monetary award. The CSC was correct to deduct and withhold the following taxes: (1) 6% of the gross receipts representing VAT under Section 114(c) of the 1997 NIRC; and (2) 1% of the gross payments representing 1% of the expanded creditable withholding tax under Section 2.57.2(E) of RR No. 02-98.
FAQs
What was the key issue in this case? | The key issue was whether a contractor is entitled to payment for extra work performed on a government project without prior approval, as required by applicable laws and regulations. |
What is a “quantum meruit” and why didn’t it apply here? | Quantum meruit is a legal principle that allows compensation for services rendered, even in the absence of a formal contract, to prevent unjust enrichment. It didn’t apply here because the government agency did not approve or consent to the extra works. |
What are implementing rules and regulations (IRR)? | IRRs provide the specific guidelines and procedures for implementing a law. In this case, the IRR of P.D. No. 1594 outlines the requirements for government infrastructure contracts. |
What is retention money? | Retention money is a percentage of the contract price withheld by the government to ensure that the contractor properly completes the project and corrects any defects. |
What is the main takeaway for contractors working with government agencies? | Contractors must strictly comply with all requirements for obtaining approval for extra work orders. Failure to do so may result in non-payment for those services. |
Why did the Supreme Court remand the case to the RTC? | The Supreme Court remanded the case to the RTC for the proper computation of the total monetary award due to the contractor, considering the adjustments made regarding withholding taxes and retention money. |
What did the Court clarify about deductions for taxes? | The Court clarified that VAT should be computed on the gross amount of each progress payment before deducting retention money, ensuring that the correct amount of tax is withheld. |
What is P.D. No. 1594? | Presidential Decree No. 1594 prescribes policies, guidelines, rules, and regulations for government infrastructure contracts. It governs the procedures and requirements for these types of projects. |
The Estomo vs. CSC case serves as a crucial reminder to contractors engaged in government projects to strictly adhere to the rules and regulations governing extra work orders. Securing prior approval and maintaining proper documentation are essential to ensure fair compensation and avoid disputes. This ruling reinforces the importance of transparency and accountability in government contracts, protecting public funds and promoting efficient project implementation.
For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.
Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: Domingo F. Estomo, vs. Civil Service Commission, G.R. No. 248971, August 31, 2022