In Filinvest Alabang, Inc. v. Century Iron Works, Inc., the Supreme Court ruled that even in fixed lump sum contracts, contractors can recover costs for additional work if properly authorized and agreed upon in writing. This decision clarifies the scope and limitations of fixed lump sum agreements in the construction industry, providing a framework for resolving disputes over extra work and ensuring fair compensation for contractors. It highlights the importance of adhering to contractual provisions regarding change orders and documenting all agreements related to additional work.
Building Bridges Beyond the Blueprint: Can Contractors Claim Extra Pay?
This case revolves around a dispute between Filinvest Alabang, Inc. (Filinvest), a property developer, and Century Iron Works, Inc. (Century Iron), a construction company. In 1997 and 1998, Filinvest awarded several contracts to Century Iron, including one for metal works at the Filinvest Festival Supermall, valued at P29,000,000.00. After completing the project, Century Iron sought full payment but Filinvest withheld P1,392,088.68, citing substandard workmanship and disputing the cost of an additional scenic elevator enclosure.
Century Iron then filed a lawsuit to recover the unpaid amount. Filinvest countered that it was justified in retaining funds due to damages caused by Century Iron’s poor work and that the lump sum nature of the contract precluded additional claims for the elevator enclosure. The central legal question was whether Century Iron could recover the withheld amounts, particularly the cost of the additional elevator enclosure, despite the fixed lump sum contract.
The Regional Trial Court (RTC) partially ruled in favor of Century Iron, awarding P227,500.00 plus legal interest, finding that Filinvest was estopped from claiming damages due to its issuance of a Certificate of Completion and Acceptance. However, the RTC denied the claim for the additional elevator enclosure, citing the lump sum nature of the contract. Century Iron appealed to the Court of Appeals (CA).
The CA affirmed the RTC’s ruling with modification, ordering Filinvest to pay the full amount claimed by Century Iron, including the cost of the additional elevator enclosure. The CA agreed that Filinvest was estopped from claiming substandard workmanship and held that the contract was not strictly fixed lump sum, allowing for additional work to be compensated. This led Filinvest to petition the Supreme Court, arguing against the CA’s decision.
The Supreme Court denied Filinvest’s petition, upholding the CA’s decision with a modification on the interest rates. The Court emphasized that factual findings of the lower courts, particularly when affirmed by the CA, are binding unless there is a clear showing of abuse or arbitrariness. Both the RTC and the CA found that Filinvest had issued a Certificate of Completion and Acceptance, estopping it from later claiming substandard workmanship.
Concerning the additional scenic elevator enclosure, the Supreme Court acknowledged the conflicting findings between the RTC and the CA, which necessitated its own determination of whether the contract was indeed fixed lump sum. The Court then cited Article 1724 of the Civil Code, which governs fixed lump sum contracts:
Art. 1724. The contractor who undertakes to build a structure or any other work for a stipulated price, in conformity with plans and specifications agreed upon with the landowner, can neither withdraw from the contract nor demand an increase in the price on account of the higher cost of labor or materials, save when there has been a change in the plans and specifications, provided:
(1) Such change has been authorized by the proprietor in writing; and
(2) The additional price to be paid to the contractor has been determined in writing by both parties.
The Court clarified that while fixed lump sum contracts generally limit the project owner’s liability to the stipulated amount, Article 1724 does not preclude parties from agreeing to additional work. The Court emphasized that to recover costs for such additional work, the contractor must demonstrate:
- A written authority from the project owner ordering or allowing the changes; and
- A written agreement on the increase in price or cost due to the change.
According to the High Court, compliance with these two requisites is a condition precedent for recovery, and neither the authority for the changes nor the additional price can be proven by any evidence other than the written authority and agreement. In this case, the Court found that the contract was indeed a fixed lump sum agreement, where Century Iron agreed to provide all materials, labor, and equipment necessary for the metal works, and Filinvest agreed to pay a lump sum of P29,000,000.00. However, this did not prevent the parties from agreeing on additional work.
The Court noted that Filinvest issued two Site Instructions pertaining to the construction of the additional scenic elevator enclosure. The valuation of this additional work was derived from the Bill of Quantities and documented in the Cost Breakdown for Claim of Change Orders and the Material Quantity Breakdown for Scenic Elevator Enclosure submitted by Century Iron to Filinvest. Because there was a written authority from Filinvest for the additional work and a written agreement on its valuation, Century Iron was entitled to recover the cost of the additional elevator enclosure.
The Supreme Court, in its decision, also addressed the applicable interest rates on the amounts due to Century Iron. The Court cited Nacar v. Gallery Frames, which provides a guideline for imposing legal interest. Specifically, the Court stated that the amounts due to Century Iron should be subject to legal interest at the rate of twelve percent (12%) per annum from extrajudicial demand until June 30, 2013, and six percent (6%) per annum thereafter until full payment, in accordance with the prevailing jurisprudence.
This case underscores the importance of clear and comprehensive contract documentation, especially when dealing with construction agreements. While fixed lump sum contracts offer certainty, they do not preclude modifications or additional work. However, to ensure enforceability and avoid disputes, any changes or additional work must be authorized in writing by the project owner, and the parties must have a written agreement on the associated costs.
FAQs
What was the key issue in this case? | The central issue was whether a contractor could recover costs for additional work performed under a fixed lump sum contract without explicit written agreements. |
What is a fixed lump sum contract? | A fixed lump sum contract is an agreement where a contractor agrees to complete a project for a specified amount, regardless of the actual costs incurred. |
What did the Supreme Court decide? | The Supreme Court ruled that even in fixed lump sum contracts, contractors can recover costs for additional work if there is written authorization and agreement on the price. |
What is the significance of the Certificate of Completion and Acceptance? | The Certificate of Completion and Acceptance signifies that the project owner accepts the contractor’s work as satisfactory, estopping them from later claiming substandard workmanship. |
What are the requirements for recovering costs for additional work? | To recover costs for additional work, there must be a written authority from the project owner and a written agreement on the price or cost due to the changes. |
What is Article 1724 of the Civil Code? | Article 1724 of the Civil Code governs fixed lump sum contracts, stating that contractors cannot demand an increase in price unless changes are authorized in writing. |
What interest rate applies to the monetary awards? | The monetary awards are subject to legal interest at 12% per annum from extrajudicial demand until June 30, 2013, and 6% per annum thereafter until full payment. |
What is a Site Instruction? | A Site Instruction is a formal directive issued by the project owner or engineer, instructing the contractor to perform additional or changed work. |
In conclusion, Filinvest Alabang, Inc. v. Century Iron Works, Inc. serves as an important reminder of the necessity for clear documentation and adherence to contractual provisions in construction agreements. While fixed lump sum contracts offer simplicity, they do not eliminate the possibility of additional work. By ensuring that all changes are properly authorized and agreed upon in writing, parties can mitigate the risk of disputes and ensure fair compensation for all work performed.
For inquiries regarding the application of this ruling to specific circumstances, please contact ASG Law through contact or via email at frontdesk@asglawpartners.com.
Disclaimer: This analysis is provided for informational purposes only and does not constitute legal advice. For specific legal guidance tailored to your situation, please consult with a qualified attorney.
Source: FILINVEST ALABANG, INC. VS. CENTURY IRON WORKS, INC., G.R. No. 213229, December 09, 2015