Quantum Meruit and Government Contracts: When Can You Get Paid for Unapproved Work?
E.L. SANIEL CONSTRUCTION, PETITIONER, VS. COMMISSION ON AUDIT AND PNOC SHIPPING AND TRANSPORT CORPORATION (PSTC), RESPONDENTS. G.R. No. 260013 [Formerly UDK 17349], August 13, 2024
Imagine a contractor who, in good faith, performs extra work on a government project, believing it’s essential. But what happens when that work isn’t formally approved? Can the contractor still get paid? This question lies at the heart of the Supreme Court’s decision in E.L. Saniel Construction vs. Commission on Audit (COA). The case clarifies the application of quantum meruit—the principle of “as much as he deserves”—in government contracts, particularly concerning unapproved variation orders and additional work.
Understanding Quantum Meruit in Philippine Law
Quantum meruit is a legal doctrine that allows a party to recover compensation for services rendered or work done, even in the absence of an express contract or when a contract is deemed invalid. It’s based on the principle of fairness and preventing unjust enrichment. This doctrine is especially relevant in construction contracts, where unforeseen circumstances often require additional work beyond the original scope.
However, when dealing with government contracts, the application of quantum meruit is subject to stricter scrutiny due to the requirements of transparency and accountability in government spending.
The Government Procurement Reform Act (Republic Act No. 9184) and its Implementing Rules and Regulations (IRR) outline the procedures for contract variations and additional work. Specifically, Annex “E” of the IRR-A addresses the issuance of Variation Orders, emphasizing the need for prior approval from the Head of the Procuring Entity (HOPE) or their authorized representative.
Annex “E”, Section 1.4 of the IRR-A of Republic Act No. 9184 states that Variation Orders may be issued by the procuring entity in exceptional cases where it is urgently necessary to complete the original scope of work, but such must not exceed 20% of the original contract price.
Section 1.5 also states that in claiming for any Variation Order, a notice should first be given to the HOPE or their duly authorized representative within seven calendar days after the commencement of additional works or within 28 calendar days after the circumstances or reasons for justifying a claim for extra cost shall have occurred—failure to timely provide notices constitutes waiver for any claim against the procuring entity.
For instance, imagine a contractor building a school. During excavation, they discover an unstable soil condition requiring extensive soil stabilization. Under RA 9184, the contractor needs to inform the HOPE immediately and secure approval for a Variation Order. Failing to do so can jeopardize their chances of getting paid for the extra work.
The E.L. Saniel Construction Case: A Detailed Look
E.L. Saniel Construction was contracted for two projects by PNOC Shipping and Transport Corporation (PSTC): the rehabilitation of the PSTC Limay Office and the construction of slope protection (Riprap Project). During construction, E.L. Saniel claimed that unforeseen terrain conditions necessitated additional work, leading to extra billings totaling PHP 2,962,942.39. PSTC did not pay these additional billings.
Following PSTC’s dissolution, E.L. Saniel filed a money claim with the Commission on Audit (COA) to recover the unpaid amount, including interest and attorney’s fees. The COA denied the claim, citing E.L. Saniel’s failure to obtain prior approval for the additional work as required by RA 9184 and its IRR.
Here’s a breakdown of the key events:
- 2010: E.L. Saniel awarded the Rehabilitation and Riprap Projects.
- During Construction: E.L. Saniel performs additional works without prior approval.
- June 6, 2011: E.L. Saniel requests payment for additional work *after* project completion.
- February 7, 2013: PNOC Board resolves to shorten PSTC’s corporate life.
- November 5, 2014: E.L. Saniel files a Petition to be Paid Money Claims with COA.
- December 17, 2016: COA dismisses E.L. Saniel’s money claim.
- August 13, 2024: Supreme Court affirms COA’s decision, denying E.L. Saniel’s petition.
The Supreme Court emphasized the importance of adhering to procedural requirements in government contracts, stating that “the bidder, by the act of submitting its bid, shall be deemed to have inspected the site and determined the general characteristics of the contract works and the conditions pertaining thereto.”
The Court also highlighted that “under no circumstances shall a contractor proceed to commence work under any Variation Order unless it has been approved by HOPE or their duly authorized representative.”
Furthermore, the Court reiterated its stance on quantum meruit, explaining that the principle can only be applied when there’s sufficient evidence of an implied contract, completion and delivery of the work, and a manifest benefit to the government. E.L. Saniel failed to provide such evidence.
Practical Implications and Key Lessons
This case serves as a cautionary tale for contractors engaging in government projects. It underscores the critical importance of obtaining prior approval for any additional work or contract variations. Failure to comply with the procedural requirements outlined in RA 9184 and its IRR can result in the denial of payment, even if the work was performed in good faith and benefitted the government.
Key Lessons:
- Always obtain prior approval for additional work: Never proceed with contract variations without formal approval from the HOPE or their authorized representative.
- Document everything: Maintain thorough records of all communications, requests, and approvals related to the project.
- Comply with procedural requirements: Familiarize yourself with RA 9184 and its IRR, and strictly adhere to the prescribed procedures for contract variations.
- Timely Notification: Notify the HOPE or authorized representative as soon as possible of any additional work.
Imagine another scenario: A contractor is hired to renovate a public library. During the renovation, they discover asbestos, requiring immediate abatement. If the contractor immediately informs the relevant government authority, documents the discovery, and seeks approval for a Variation Order, they are more likely to be compensated for the additional asbestos removal work.
Frequently Asked Questions (FAQ)
Q: What is quantum meruit?
A: Quantum meruit means “as much as he deserves.” It’s a legal doctrine that allows a party to recover reasonable compensation for services rendered or work done, even without an express contract.
Q: When can quantum meruit be applied in government contracts?
A: In government contracts, quantum meruit can be applied in exceptional cases where there’s evidence of an implied contract, completion and delivery of the work, and a clear benefit to the government. However, strict compliance with procurement laws is generally required.
Q: What is a Variation Order?
A: A Variation Order is a written order issued by the procuring entity to modify the original scope of work in a construction contract. It typically involves changes, additions, or deletions to the work.
Q: What happens if I perform additional work without prior approval?
A: Performing additional work without prior approval can jeopardize your chances of getting paid. The government may deny your claim for compensation, even if the work was necessary and beneficial.
Q: What should I do if I encounter unforeseen circumstances during a government project?
A: Immediately notify the HOPE or their authorized representative, document the circumstances, and seek approval for a Variation Order before proceeding with any additional work.
Q: What is the importance of the Head of Procuring Entity (HOPE)?
A: The HOPE, or their duly authorized representative, is the only person that can approve any changes or extra work that entails costs to the government. Their signature is critical in all variation orders.
ASG Law specializes in government contracts and procurement law. Contact us or email hello@asglawpartners.com to schedule a consultation.